Defining IEDs and starting the IEC 61850 Configuration tool - Arc protection - Bay control and measurement - Motor protection - Transformer protection - 2 winding - Busbar differential protection (low impedance) - Feeder protection - Voltage regulation - Busbar protection (voltage and frequency) - Capacitor bank protection - Interconnection protection - Power management/Load shedding - Back-up protection - Engineering Manual - SSC600 Smart substation control and protection - 1.5 - IEC - ANSI - 17.04.2023

SSC600 and SSC600 SW Engineering Manual

Use PCM600 to define the substation and the IEDs. Before starting the system engineering, configure the IED settings and logic in PCM600.
Note: For more information, see PCM600 documentation.
  1. Create a PCM600 project with all the needed IEDs.
    Note: If the substation includes third party IEDs requiring configuring for horizontal GOOSE communication, instantiate a generic IEC 61850 IED under the substation in the plant structure and import the SCL files (ICD/CID) holding the information on those IEDs. The third party IEDs have separate tools for creating the ICD/CID/SCD file.
  2. Start the IEC 61850 Configuration tool.
    Figure 1. Starting IEC 61850 Configuration