- Select the IED node in Plant Structure in Project Explorer.
- Click the Report Controls tab.
-
Right-click the area containing the existing report control blocks and select New to add a new report control block.
Figure 1. Adding a new report control block - Browse to LLN0 under LD0 to define where to place the report control block.
- Give a unique name to the report control block.
-
In the drop-down list, select the previously created data set to link with the GCB.
Figure 2. Data set drop-down list -
Edit the properties and options of the created report control block.
Figure 3. Report control block properties Note: Data set entries in a data set linked to the GCB can be modified from the GCB Control Block tab by selecting the Data Set Details in the shortcut menu.