Configuring GOOSE with the IEC 61850 Configuration tool - Arc protection - Bay control and measurement - Motor protection - Transformer protection - 2 winding - Busbar differential protection (low impedance) - Feeder protection - Voltage regulation - Busbar protection (voltage and frequency) - Capacitor bank protection - Interconnection protection - Power management/Load shedding - Back-up protection - Engineering Manual - SSC600 Smart substation control and protection - 1.5 - IEC - ANSI - 17.04.2023

SSC600 and SSC600 SW Engineering Manual

See detailed descriptions of the steps in corresponding chapters.

  1. Add devices to a PCM600 project.
  2. Engineer the GOOSE connections between the devices.
    1. Define the published GOOSE data and control blocks.
    2. Define the subscribing IEDs for the GOOSE data.
  3. Engineer the IED applications with GOOSE inputs.