Sample data interruptions - Arc protection - Bay control and measurement - Merging unit - Operation Manual - SMU615 Substation Merging Unit - 1.0 - IEC - ANSI - 16.02.2023

SMU615 Operation Manual

Occasionally protection relays can receive corrupted or faulty measurement data during runtime. In these cases the operation system halts the corresponding application execution until correct data is received. In case of permanent faults, the measurement chain should be checked to remove the origin of the faulty measurement data.
Note: In case of persistent faults originating from protection relay's internal faults, contact ABB for repair or replacement actions.