The physical inspection of wiring connections often reveals the wrong connection for phase currents or voltages. However, even though the phase current or voltage connections to protection relay terminals might be correct, wrong polarity of one or more measurement transformers can cause problems.

  • Check the current or voltage measurements and their phase information from Main menu > Measurements.
  • Check that the phase information and phase shift between phases is correct.
  • Correct the wiring if needed.
  • Check the actual state of the connected binary inputs from Main menu > Monitoring > I/O status > Binary input values.
  • Test and change the relay state manually in Main menu > Tests > Binary outputs.