Configuring GOOSE inputs with IEC 61850 Configuration - Arc protection - Auto synchronization - Bay control and measurement - Merging unit - Transformer protection - 2 winding - Feeder protection - Voltage regulation - Capacitor bank protection - Petersen Coil control - Grid automation - Busbar differential protection (high impedance) - Back-up protection - Motor protection - Busbar protection (voltage and frequency) - Transformer protection - 3 winding - Interconnection protection - Generator protection - Power management/Load shedding - IEC 61850 Engineering Guide - REX640 Protection and control - Relion Protection and Control - PCL6 - IEC - ANSI

REX640 IEC 61850 Engineering Guide

  1. Select the IED node from the plant structure in the Project Explorer window.
  2. Click the GOOSE Controls tab in the tool pane.
    The rows of the GCB client editor show GCBs, the so-called senders, and the columns show the IEDs available as the GOOSE clients, the so-called receivers.
    All IEDs that are configured in the plant structure automatically appear in the clients column.
  3. To add or remove clients for a GOOSE control block, click the check-box in the grid corresponding to the IEDs.
    When adding or removing clients, the input sections of the corresponding IEDs are updated.
Figure 1. GCB client editor showing the senders and receivers
image/svg+xml211
1
Subscriber
2
Publisher
Note: On the Data Sets tab, the clients are mapped automatically to the corresponding data sets based on the configuration done on the GOOSE Controls tab and vice versa.