Create a new plant structure in one of the alternative ways.
- Right-click the Plant Structure view, point to New and select Create from Template.
- Right-click the Plant Structure view, point to New, select General and select either IED Group or Substation.
- On the View menu, select Object Types.
-
Select the needed elements and drag them into the plant structure.
Figure 1. Project with IEDs placed but not renamed -
Rename each level in the structure by the names or identifications used in the grid.
Use one of the alternative ways.
- Right-click the level and select Rename.