Test Records - Arc protection - Bay control and measurement - Merging unit - Transformer protection - 2 winding - Feeder protection - Voltage regulation - Capacitor bank protection - Grid automation - Busbar differential protection (high impedance) - Line differential protection - Back-up protection - Motor protection - Busbar protection (voltage and frequency) - Interconnection protection - Generator protection - Power management/Load shedding - Operation Manual - REX615 Protection and control - PCL2 - IEC - ANSI - 16.02.2023

REX615 Operation Manual

During pre-commissioning, commissioning, and periodical testing stages it is important to record the test cases and test results. The records shall be on such a detailed level that they can be used to detect any signs of protection performance deterioration during the years. The history shall be available for the technician performing the testing, and for a person evaluating and approving the test result.