Checking VT circuits - Arc protection - Bay control and measurement - Merging unit - Transformer protection - 2 winding - Feeder protection - Voltage regulation - Capacitor bank protection - Grid automation - Busbar differential protection (high impedance) - Line differential protection - Back-up protection - Motor protection - Busbar protection (voltage and frequency) - Interconnection protection - Generator protection - Power management/Load shedding - Operation Manual - REX615 Protection and control - PCL2 - IEC - ANSI - 03.05.2023

REX615 Operation Manual

Check that the wiring is in strict accordance with the supplied connection diagram.

Note: Correct possible errors before continuing to test the circuitry.

Test the circuitry.

  • Polarity check
  • VT circuit voltage measurement (primary injection test)
  • Earthing check
  • Phase relationship
  • Insulation resistance check

The polarity check verifies the integrity of circuits and the phase relationships. The polarity must be measured as close to the protection relay as possible to ensure that most of the wiring is also checked.

The primary injection test verifies the VT ratio and the wiring all the way from the primary system to the protection relay. Injection must be performed for each phase-to-neutral circuit and each phase-to-phase pair. In each case, voltages in all phases and neutral are measured.