SMV Simulation - Arc protection - Bay control and measurement - Merging unit - Transformer protection - 2 winding - Feeder protection - Voltage regulation - Capacitor bank protection - Grid automation - Busbar differential protection (high impedance) - Line differential protection - Back-up protection - Motor protection - Busbar protection (voltage and frequency) - Interconnection protection - Generator protection - Power management/Load shedding - IEC 61850 Engineering Guide - REX615 Protection and control - Relion Protection and Control - PCL2 - IEC - ANSI - 14.05.2025

REX615 IEC 61850 Engineering Guide

Relay is capable of processing simulated messages. The switchover to simulated messages requires that the relay is set to allow simulated messages and that it receives the first simulated message. Detection of simulated messages is separated per SMV publisher. Therefore, one SMV stream may receive as simulated while another stream is received as a non-simulated one.

To set the protection relay to allow simulated SMV, either LD0.LPHD1. Sim is set to true via the IEC 61850 protocol or the Tests > IED Test > Allow simulation parameter is set via the WHMI or the LHMI to "Yes".

Switching back to receiving only non-simulated normal SMV stream requires that the Allow simulation parameter is set to "No" (or LD0.LPHD1.Sim = false). The values change to real ones after the first received normal SMV packet after simulation mode has been disabled.

The simulation mode behavior is described in more detail in IEC 61850-7-1 standard section. To monitor if the SMV stream(s) received by the relay is simulated or not, check HMI: Monitoring > IED status > SMV traffic > SMVRCVx > Simulation status.