Network configuration - Arc protection - Bay control and measurement - Merging unit - Transformer protection - 2 winding - Feeder protection - Voltage regulation - Capacitor bank protection - Grid automation - Busbar differential protection (high impedance) - Line differential protection - Back-up protection - Motor protection - Busbar protection (voltage and frequency) - Interconnection protection - Generator protection - Power management/Load shedding - IEC 61850 Engineering Guide - REX615 Protection and control - PCL2 - IEC - ANSI

REX615 IEC 61850 Engineering Guide

Before starting the FPN configuration of the relay, the ABB-specific configuration must be correct.

  • Potential additional subnetwork must be configured using PCM600 configuration.
  • The IED's access point must be defined using Ethernet Configuration in PCM600.
  1. In PCM600, right-click an IED in the plant structure and select Options.
  2. Enable the IEC 61850 configuration engineering mode.
    Figure 1. Enabling IEC 61850 configuration engineering mode
  3. On the toolbar, select Subnetwork configuration from the drop-down list.
    Figure 2. Subnetwork configuration for REX615
  4. Configure Ethernet ports in Ethernet Configuration.
    Figure 3. Configuring Ethernet ports