Use PCM600 to define the substation and the IEDs. Before starting the system engineering, configure the IED settings and logic in PCM600. Note: For more information, see PCM600 documentation.
-
Create a PCM600 project with all the needed IEDs.
Note: If the substation includes third-party IEDs requiring configuring for horizontal GOOSE communication, instantiate a generic IEC 61850 IED under the substation in the plant structure and import the SCL files (ICD/ CID) holding the information on those IEDs. The third-party IEDs have separate tools for creating the ICD/CID/ SCD file.
-
Start the IEC 61850 Configuration.