Defining IEDs and starting IEC 61850 Configuration - Arc protection - Bay control and measurement - Merging unit - Transformer protection - 2 winding - Feeder protection - Voltage regulation - Capacitor bank protection - Grid automation - Busbar differential protection (high impedance) - Line differential protection - Back-up protection - Motor protection - Busbar protection (voltage and frequency) - Interconnection protection - Generator protection - Power management/Load shedding - IEC 61850 Engineering Guide - REX615 Protection and control - PCL2 - IEC - ANSI - 14.02.2023

REX615 IEC 61850 Engineering Guide

Use PCM600 to define the substation and the IEDs. Before starting the system engineering, configure the IED settings and logic in PCM600.
Note: For more information, see PCM600 documentation.
  1. Create a PCM600 project with all the needed IEDs.
    Note: If the substation includes third-party IEDs requiring configuring for horizontal GOOSE communication, instantiate a generic IEC 61850 IED under the substation in the plant structure and import the SCL files (ICD/ CID) holding the information on those IEDs. The third-party IEDs have separate tools for creating the ICD/CID/ SCD file.
  2. Start the IEC 61850 Configuration.