Use PCM600 to define the substation and the IEDs. Before starting the system engineering, configure the IED settings and logic in PCM600.
Note: For more information, see PCM600 documentation.
  1. Create a PCM600 project with all the needed IEDs.
    Note: If the substation includes third party IEDs requiring configuring for horizontal GOOSE communication, instantiate a generic IEC 61850 IED under the substation in the plant structure and import the SCL files (ICD/CID) holding the information on those IEDs. The third party IEDs have separate tools for creating the ICD/CID/SCD file.
  2. Start the IEC 61850 Configuration tool.
    Figure 1. Starting IEC 61850 Configuration
    image/svg+xml